Board Building and Grounds: Difference between revisions
Jump to navigation
Jump to search
→Late March to Early April: Water and Pool Opening
Matt Parnell (talk | contribs) |
Matt Parnell (talk | contribs) |
||
| Line 27: | Line 27: | ||
=== Late March to Early April: Water and Pool Opening === | === Late March to Early April: Water and Pool Opening === | ||
Opening day for members is typically scheduled for the Thursday before Memorial Day (which is the last Monday in May). | |||
* Request water meter installation via the City of Livonia. The city installs approximately 1,500 seasonal meters, so request early. Typically, meter installation begins in late March. | * Request water meter installation via the City of Livonia. The city installs approximately 1,500 seasonal meters, so request early. Typically, meter installation begins in late March. | ||